This article explains Lab Planning, how it works, and why it matters.
Lab Planning
Lab Planning refers to EERE Technology Offices and Laboratories annually collaborate to finalize project details into an Annual Operating Plan (AOP).
Prior to each fiscal year (FY), EERE Technology Offices work in collaboration with each Laboratory to plan and negotiate the scope, schedule,
and budget for each project and once all project details have been finalized, the details are compiled into a document called the
Annual Operating Plan (AOP). Each office has one AOP for each Laboratory they work with.
When/Why It’s Used
The planning of lab projects occurs annually in Lab Planning within PM Bridge.
New Lab Planning in PM Bridge Key Changes and Benefits
Key Changes
- Offices only create a Lab Project once, documenting the full multi-year period of performance
- Projects can be modified at any time through an approval workflow process, eliminating the annual change control process
- Required data is reduced to focus on key project details needed for budget planning and execution
Benefits
- Consolidates multiple, disparate systems into a single data-centric project management system
- Restructures lab data to align with financial assistance data to enhance EERE portfolio data and budget analysis
- Reduces manual burden of redundant data entry caused by current process of copying projects every year & reducing required fields for project approval
Pathways to Lab Projects
There are three different ways that EERE can initiate a project to a National Lab.
• Labs can apply as a prime recipient or a subrecipient of a Notice of Funding Opportunity (NOFO).
• Labs can apply to a Lab Call
• Labs can be Directly Funded for specific research initiatives or lab projects.
Lab Planning Process
NOFOs and Lab Calls are published and selected in EPIC and projects are manually entered into PM Bridge, including Directly funded Lab Projects,
which will continue to require manual entry. Data from the selected lab calls and NOFOs will soon automatically update to the lab planning module in PM Bridge.
From here the lab project is created and the office or lab updates the project.
The technology office and lab work together, maintaining a communication loop until the project details are finalized.
Once the project has been finalized, the project is routed through an approval workflow to gain final approval.
Remember, projects can be modified at any time.
Project data is automatically synced nightly in CPS to support Budget Execution and once approved, lab projects will be available in PM Bridge.
You can view the full R&D portfolio in PM Bridge.
Lab Planning Workflow
By default, all projects will require approval from the EERE Project Lead, Office Administrator, and Office Director.
However, there is an option to add additional approvers to the workflow (including Lab staff such as Principal Investigator,
Lab Relationship Manager, and Lab Operations POC), if desired.
Once the project has gone through the approval workflow, the by default workflow, or with a modified approval workflow,
the lab will be notified once the project is approved.
Lab Planning Modifications
After a project has been approved, modifications can be made at any time. Identify the modification type.
Enter the modification details. Changes are tracked in Change History. Submit the modified project for approval.
The project is routed through the approval process and approved.