Article: How to Manage Projects in CPS
Related Articles
| Content by Label | ||||||||
|---|---|---|---|---|---|---|---|---|
|
| Panel | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ||||||||||||
This article guides you through managing projects in the system, including creating, viewing, editing, and moving them in the system. |
View a Project
- To access the List Project page, navigate to Portfolio Management on the content function menu and click View Solicitation/Project/Agreement. Select the Projects radio button.
- Specific Object Selection: If a project is selected in the left menu, the content frame will display its edit form.
- Folder Selection: If a folder is selected, the content frame will list projects within that folder. You can Edit or View individual items from this list by clicking the appropriate link.
- Filter Options: When listing solicitations, projects, or agreements, you can check the "Limit to crosscut projects only" box to filter the list.
Edit a Project
- There are two primary ways to edit a project:
From the List Solicitations/Projects/Agreements Screen
Go to the List Projects screen.
- Click Edit next to the desired project in the final column to bring up the Project Edit form.
- Alternatively, click View to see the project information without making changes.
Using the Left-Hand Menu Navigation
- Select the project in the left-hand navigation menu
- Hover over Portfolio Management on the content function menu and click View Solicitations/Projects/Agreements to open the project edit screen.
- Project Edit Form Details - When you edit a project, you will encounter several sections:
- Basic Information - Complete the required fields marked with a red asterisk. Optional fields include:
Formal Title (required): Enter the official spend plan title used by the government. This title should be distinct from the short title. Changes to this field will apply to all years associated with this project.
Short Title (annual) (required): Provide a concise title for managers to easily reference the project. You can vary this title for a selected year on the project.
Description (required): Clearly describe the project's purpose and its technical objectives. Edits to this description will update it for all years associated with the project.
- Major FY Activities (annual) (optional): Describe the annual scope of work for this project. You can customize this description for a selected year.
- Project Type (optional): Select the type of work performed from the dropdown menu. Changing this type updates it for all associated years.
Project Status (required): Choose the current status of your project from the dropdown menu. Note: Projects marked "active" but lacking an active agreement will be considered inactive. Updates to this status will affect all years associated with the project.
Technology Manager (annual) (required): Select the technology program manager from the dropdown menu. This selection can be varied for a selected year on the project.
Budget Analyst (required): Choose the budget analyst from the dropdown menu. Changes here will update the budget analyst for all years associated with the project.
Start Date (required): This field defaults to the project creation date. To change it, click the ellipses to open a calendar and select a new date, or type the date manually. Modifying this date affects all years associated with the project.
Completion Date (Required): Select the project's completion date using the calendar (by clicking the ellipses) or by typing it in manually. This date defaults to the last day of the selected fiscal year. Note: The completion date must be later than the start date; otherwise, the system will display an error message. Modifying this date affects all years associated with the project.
Belongs to SBIR/STTR? (optional): Check this box for "Yes" or leave it unchecked for "No." Your selection here will apply to all associated years. Note that you cannot select this for projects located in business administration or DOE crosscut folders, as SBIR/STTR projects must reside in the technology development folder.
- ARRA Project Code (optional): This field appears only if your project is within the Recovery Act folder. Enter the recovery act project code here.
Update Current Year: Click this button to save your changes for the current year. If the project's start and completion dates fall outside the fiscal year currently selected in the left menu, the project will no longer appear there, and you will need to select the appropriate fiscal year to find or edit it.
- Show Multiple Year Update Options: If your project spans multiple fiscal years, you can choose which annual data fields and fiscal years to update. Click this button to reveal a section listing all annual data fields and active fiscal years. Check the boxes next to the fiscal years and data fields you wish to update, then click Update Multiple Years to save. To save only for the selected fiscal year and hide these options, click Hide Multiple Year Update Options before clicking Update Current Year.
- Funding Authorizations - Shows your approved and planned program guidance with their associated B&R Codes.
- View All Years: Click this to see past and future guidance. For projects where funds are broken out to agreements, click the Detail link in the last column of either table to view all agreements, funding amounts, funding sources, and prime awardees for the selected guidance and its planned obligations.
- Costs & Obligations - CPS administrators can view cost and obligation data at the project level. This tab presents a table with all agreements for the selected fiscal year and summary calculations for each.
- Click View All Years at the bottom of the page to display all agreements over the project's lifetime.
- Clicking on any agreement within the selected fiscal year will open its edit page.
- Please note: for projects with agreements linked to STARS, the preceding month's IDW data will not include cost accruals until the month-end data becomes available in the IDW
- Milestones - View, edit, or create new technical milestones for your project.
- Documents - Manage files, URLs, and text documents linked to your project.
- Use the actions menu to edit, view, delete, hide, or show the documents.
- To add new documents, click Add New Project Document and complete the required fields.
- Direct/Related - This tab will only appear if you have been granted Direct/Related permission.
- Direct (optional) - Identify the CMEI programs and industries that directly fund your project. From the scroll down menu, click on the desired program and then click the Add double arrow to move it to the Applied to Project field. (Hold the control key to select multiple organizations.) To remove a program, select it from the Applied to Project field and click the Remove double arrow.
- Related (optional) - Identify the CMEI programs and industries that categorize your project; these essentially act as keywords. From the scroll down menu, click on the desired program and then click the Add double arrow to move it to the Applied to Project field. To remove a program, select it from the Applied to Project field and click the Remove double arrow.
- Agreements - Refer to How to Manage Agreements for detailed instructions on how to create or edit an agreement.
- Basic Information - Complete the required fields marked with a red asterisk. Optional fields include:
Create a Project
- To create a new project, ensure you select the correct fiscal year and folder in the Navigational Menu where the project should reside.
- Select a folder by clicking on it in the left menu or by clicking its name next to the folder icon.
- Next, hover your pointer over Portfolio Management in the content function menu and select Create Project. The fields required to create a project are identical to those described in the "Edit Project" section.
| Panel | ||||||
|---|---|---|---|---|---|---|
| ||||||
|
Move a Project
In the Left-Hand navigational menu, locate and select the project you wish to move.
Left-click and hold the mouse button on the project you want to move. Drag your pointer to the intended folder.
The system will present a confirmation message asking if you want to move the project for all fiscal years it exists or just for the currently selected fiscal year.
Frequently Asked Questions
Q: Why can't I create a project in a specific folder?
A: If the folder is a non-business administration type and requires a project-level milestone, you might be unable to create a project if your user role does not include the ability to create milestones.
Q: I edited a project's start date, but now I can't find the project. What happened?
A: If you updated the project's start or completion dates so they fall outside the currently selected fiscal year in the left menu, the project will no longer appear in that menu view. To find it, you need to select the appropriate fiscal year from the left menu that encompasses the project's new dates.
Q: Can I choose which specific changes apply to prior or future years of a multi-year project?
A: Yes, when editing a project that spans multiple fiscal years, use the "Show Multiple Year Update Options" feature. This allows you to select specific annual data fields and fiscal years to update, giving you granular control over how changes are propagated.
Q: Why does a project that is marked 'active' seem inactive?
A: The system treats 'active' projects as inactive if they do not have an active agreement associated with them. Ensure an active agreement is in place if you expect the project to be fully active.
Related Articles
| hidden | true |
|---|
| Optics Button | ||||
|---|---|---|---|---|
|