This article answers common questions about the migration of Project Management Center (PMC) functions and data to Project Management Bridge (PM Bridge). It covers the transition schedule, project data, recipient access, NEPA packages, Federal Assistance Reporting Checklists (FARCs), reporting requirements, and project locations.

Transition Time and Approach

Q: When will PMC functionality transition to PM Bridge?

A: Beginning November 16, 2026, the following PMC functions will transition to PM Bridge: NEPA Management, including preparation of EQ-1, EQ-2, and NEPA Determination documentation; Federal Assistance Reporting Checklist (FARC) creation and management; Financial Assistance recipient reporting; and project deliverable management.

Q: Will PMC be retired?

A: Yes. PMC will be retired in FY 2027. The external-facing portion of PMC will be retired by January 30, 2027, and the system will then remain available only to internal users until full retirement.

Q: Can I continue to use PMC until it is retired?

A: Business functions must be performed in PM Bridge after November 16, 2026. Internal CMEI users may access PMC for historical purposes until the system is retired later in FY 2027.

Q: Why is CMEI transitioning from PMC to PM Bridge?

A: CMEI is transitioning from PMC to PM Bridge to better satisfy cybersecurity requirements and modernize data management and functional capabilities.

Q: Is this transition only for the Golden Field Office?

A: No. All CMEI Financial Assistance project actions managed by either the Golden Field Office or NETL are being migrated.

Q: Will Lab recipients be able to submit project deliverables to PM Bridge?

A: No. At this time, Lab recipients cannot submit project deliverables directly to PM Bridge. This capability is planned as a future enhancement.

Q: This transition feels rushed. Can we have more time using PMC before we use PM Bridge?

A: Pending cybersecurity requirements affecting PMC required an accelerated transition. The new functionality will be available in PM Bridge beginning November 16 for CMEI staff. Financial Assistance recipients will be able to access PM Bridge starting December 1. December provides users an opportunity to explore the functionality before FY 2027 Quarter 1 reporting is due in January.

Project Data

Q: My project is not available in PM Bridge. What should I do?

A: Contact the CMEI Help Center for assistance if your project is missing from PM Bridge.

Q: How do Financial Assistance projects become available in PM Bridge?

A: PM Bridge imports Financial Assistance projects when applications are identified for selection in Exchange or when projects are awarded in STRIPES.

Q: Will newly selected awards use PM Bridge for the NEPA process?

A: Yes. Selectees in award negotiation should be directed to PM Bridge to submit their EQ-1s. For existing PMC projects that are in PM Bridge, completed and in-progress NEPA packages are being migrated, except for EF forms. PMC will be sunset in FY 2027, with external functionality disabled by January 31, 2027.

Q: Will project data from PMC be migrated to PM Bridge?

A: Yes. Active project data from PMC will be migrated to PM Bridge.

Q: Are awards that are "In Closeout" being migrated from PMC to PM Bridge?

A: Yes. If a project exists in PM Bridge, it will be migrated even if its PMC status is "In Closeout."

Q: Will awards past their period of performance but not yet closed out be migrated so recipients can submit final deliverables?

A: Yes. If a project exists in PM Bridge, it will be migrated even if its PMC status is "In Closeout" or "Closed."

Q: The data on my project is incorrect. What should I do?

A: Contact the CMEI Help Center for assistance if your project data in PM Bridge is incorrect.

Q: Why do my project locations have all the data in a single field?

A: Because of migration complexities, some project location data was imported and stored in a single field. Users can edit locations imported from PMC and correct the data.

Q: Why was my project data not migrated from PMC?

A: Only projects that already existed in PM Bridge had PMC data migrated. When PM Bridge first went online, only projects active as of spring 2023 were made available, so projects closed before then do not exist in PM Bridge.

Q: Are projects that were terminated but are in dispute considered active?

A: Award status in PM Bridge is populated from EDC, which receives nightly STRIPES data. If a project is "Cancelled" in STRIPES, it displays as "Closed" in PM Bridge. All PMC projects that exist in PM Bridge, regardless of status, will have their data, NEPA packages, FARCs, and associated recipient deliverables migrated. If project data or documents are missing, contact the CMEI Help Center.

Recipient Access

Q: How does a recipient get access to a project?

A: Project recipients, including the Business Contact and Principal Investigator, are imported from the STRIPES record. A recipient listed as a recipient team member on a project will have access to the project record.

Q: What do I do if there are no Recipient Team Members associated with my project?

A: A DOE Team Member can manually add recipient team members to the project in PM Bridge.

Q: Will recipients use PM Bridge only to submit the EQ-1?

A: No. Recipients will use PM Bridge to submit both their EQ-1 and their deliverables.

Q: How do recipients get started? Are training guides available?

A: From the PM Bridge home page, recipients can access training materials covering registration, EQ-1 submission, and report and deliverable submission.

NEPA Packages

Q: On my NEPA form, why is some data different in PM Bridge from what appears in PMC?

A: For NEPA forms that are in progress, PM Bridge pulls certain field values from the project record. To change those values, update the source system, such as STRIPES. Project contacts may also be added directly in PM Bridge.

Q: Why is the announcement number missing on my NEPA forms?

A: Some Announcement Numbers could not be migrated. DOE users can edit the EQ-2 form to update the Announcement Number for the project.

Q: Why do my reporting requirements look different in PM Bridge than they did in PMC?

A: The most recently published FARC data from PMC was migrated for active projects to create the reporting requirements list in PM Bridge. Some historical reporting requirement uploads may not appear on the Reporting Requirements tab. All migrated project documents, including deliverables not shown on that tab, are available in the project Document Library.

Q: Can I run a portfolio report that includes locations of work entered through NEPA?

A: Yes. The CMEI Investment Map includes the primary locations of work for all active CMEI projects. It provides a heat map and project details and can be filtered by Pillar or Office, Financial Assistance or Lab, State, ZIP Code, or Congressional District.

Q: How frequently is STRIPES data, including Requisition Numbers, refreshed?

A: STRIPES data is pulled into EDC nightly and then pulled into PM Bridge.

Q: Why is some data on the NEPA forms not visible in PM Bridge?

A: PM Bridge hides some questions when they do not need to be answered based on a response to another question. PMC did not work the same way, so questions that were optional may still have been completed there. To view that data, use PMC while it remains available or contact the CMEI Help Center for assistance.

Q: I unsubmitted a migrated NEPA form and resubmitted it. Why is the PDF not populated correctly?

A: For imported NEPA forms created with an older template, PM Bridge cannot populate the data into the current PDF format. Use the View action to open a read-only version of the submitted form and print the page from your browser if needed.

Q: I updated and resubmitted my NEPA Determination. Why are the EQ-1 and EQ-2 forms not updating to Final?

A: Some migrated forms do not have all currently required fields completed. For the full NEPA package to display as "Final," return to the EQ-1 and EQ-2 forms and complete any missing required data.

Q: When I view a NEPA form, why does it appear incomplete?

A: PM Bridge web forms use the current form templates. Migrated forms based on older templates may not contain all fields now required. The available data was migrated. If needed, un-submit the form in PM Bridge and complete the required fields.

FARCs and Reporting Requirements

Q: What should I do if the wrong FARC template is loaded on my project?

A: PM Bridge automatically selects a FARC template based on project type. BASE and CDS projects use the BASE FARC template; IIJA and IRA projects use the IIJA/IRA FARC template. If the wrong template is loaded, contact the CMEI Help Center.

Q: Who can edit a FARC?

A: Assigned DOE team members with the Project Lead, Project Editor, Technical Project Officer, Technology Manager, or Contract Support role can create or edit a FARC. DOE Program Office staff with the Office Administrator or Office Project Editor role can also create or edit FARCs for projects in their office.

Q: If project dates change because of a time extension but reporting requirements remain the same, must the FARC be republished?

A: Yes. A new FARC must be created and published with the new dates. When a new FARC is created after a FARC has already been published, the new FARC is prepopulated with the previously published reports and dates so they can be edited.

Q: Should a FARC be published after the modification has been signed?

A: To publish a FARC in PM Bridge, the FARC must have an approved Requisition Number. The modification must be processed in STRIPES so the status can move to EDC and then to PM Bridge.

Q: Will unacknowledged or unpublished FARCs in PMC be migrated to PM Bridge?

A: Yes. In-progress or unacknowledged FARCs will be migrated. If the FARC uses the current template, you may publish it in PM Bridge or cancel it and create a new one. If it uses an older template, you may publish it, but the PM Bridge-generated file may not be accurate because only the current template is supported. You may instead upload the PMC-exported version, or cancel the migrated FARC and create a new FARC using the latest template.

Q: Can we turn off notifications?

A: Yes. On the Reporting Requirements tab, users can turn off Deliverable Tracking Notifications. This stops upcoming and delinquent notifications to the recipient. Noncompliant notifications will still be sent internally to DOE contacts.

Q: Is turning off notifications the same as waiving a deliverable requirement?

A: No. To waive a requirement, use the Exclude Reporting Requirement action and enter comments explaining the exclusion. Once excluded, the requirement is no longer visible to recipients.

Q: Will PM Bridge notify recipients about upcoming and delinquent reporting due dates?

A: Yes. PM Bridge notifies recipients when reporting due dates are approaching and when a report is delinquent.

Q: Why are some recipient report documents missing in PM Bridge?

A: Certain file types, including ZIP and executable files, were excluded from the migration and are not available in PM Bridge.

Q: Why does my generated FARC look incorrect?

A: A FARC created with an older version of the FARC template may not generate correctly. FARCs created with the current template will display correctly.

Project Locations

Q: Why do imported project locations appear in a single field?

A: Because of migration complexities, some project location data was imported and stored in a single field. Users can edit locations imported from PMC and correct the data.



Content by Label
cqllabel = "tags"

Optics Button
macroIdtZQ4UtHlceCqB3iTmBs8s
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